Collecting historic data, either for benchmarking purposes or for use in calibrating future software estimates, can seem a daunting task without a clear and easy to follow set of guidelines. Fortunately, if a few simple and practical rules are followed, most organizations find the hurdles to successful reconstruction of completed projects are easily overcome. This document describes a method for jump starting the data collection process with minimum effort to get maximum value. The basic data requirements for calibrating estimates and assessing productivity are:
The best way to derive schedule and effort for completed projects is to reconstruct the project staffing profile. Even if the required data is easily obtainable, the interview process itself lends valuable insight into the data. If effort information is not readily available, a project manager can reconstruct the project’s staffing and effort profile in 10-20 minutes via a simple interview process.
On a piece of paper, draw a simple graph with elapsed calendar time in months on the horizontal axis as shown in the illustration. The vertical axis will be full time equivalent staffing (the total skilled manpower required to design, build, integrate, test, document, and manage the project) per month.
Ask "When did the project start?" and "How many people did you have working on it?" Next, "How long did you remain at that staffing level?" As the interviewee responds, sketch in the first staffing increment, then continue reconstructing staffing increments until the entire profile is complete.
The next step is to ask when major milestone events occurred and mark them clearly on the timeline (this will be help you determine where the major phases begin and end).
See the section on QSM Default Phase Definitions for more information on mapping the lifecycle.Add up the total effort under the staffing profile by integrating the staffing curve. For example, (2 people for 3 months = 6 staff months) plus (3 people for 7 months = 21 staff months) plus (4 people for 3 months = 12 staff months). Add the figures up like this: (6+21+12) = 39 staff months of effort over (3+7+3) = 13 calendar months. Your effort and schedule profile is complete. If you are used to seeing effort in person hours rather than person months, simply multiply the total person months of effort by whatever number the project (or your organization) considers to be the average number of person hours in the accounting month.
Next, extract the size of the system by asking for the new and modified source code or function points (or whatever sizing metric is being used). If you are using a function unit (function points, screens, tables, dialogs, etc.) other than lines of code, try to determine the average number of basic work units per size unit. If you need help in determining a gearing factor, see the Sizing section of the User Manual for additional guidance.
Finally, ask for the total number of defects found from the start of system level testing (the point at which all subsystems have been integrated. This typically starts at approximately 71% of the Build and Test phase and continues until the software product is verified as complete by the software developer and delivered to the first external installation. Also, ask for the Mean Time to Defect, or MTTD (average amount of time in days that the software was able to operate until encountering a defect) in the first month of operation. This is all the minimum information needed to calibrate the project.
[IMAGE] Example Historical Staffing Profile
There are nearly as many lifecycle methodologies as organizations that embrace them. To make matters even more complicated, even organizations that use the same methodologies often implement them differently; each applying their own terminology and slicing and dicing the work to be done in unique ways. This creates a challenge for analysts seeking to benchmark or measure across an industry that lacks a single, unifying standard or set of measures.
Rather than create yet another level of complexity, QSM has mapped the activities that occur in every software development to four high level sets of activities, or “phases”. At a high level, these phases map to the traditional set of activities common to all software projects:
This process has been jokingly described as “Deciding to do something, Determining what to do, Doing it, and Cleaning up afterwards”.
The precise words used to describe these activities are not important. What matters is that this approach is both practical and flexible. QSM didn’t set out to describe waterfall, iterative, agile, Rational, or any other method; those are all micro views of a more general process in which certain elements are usually present. Our approach addresses fundamental issues every project faces, but though these activities are common to all software projects, in practice not all of these activities will be recorded for every software project.
In fact, our database shows many activities are routinely handled by outside groups. Frequently the initial go/no-go decision is made by a group which then has no further involvement with the project. Post-implementation support is often performed by a production support team. Overall, about:
When deciding which phases to capture historical data for post-implementation, practicality is often the best guide. Ask: “What activities do we most need to estimate and/or benchmark?” and focus your data collection activities accordingly. If the go/no-go decision is handled externally or there is no consistent process for this phase, it may more sensible to concentrate data collection efforts on phases for which you have consistent and readily available data.
Though many different lifecycle models exist, all of these models have certain elements in common. Moreover, these common elements occur in the same general order. For each developed software element, Requirements definition begins before Design, which precedes Coding, which is followed by Integration and testing (RDCI). The SLIM model has been used successfully for many years to model Waterfall, Spiral, Incremental, and many other development methodologies.
The program being estimated or reconstructed doesn't have to be developed according to the default QSM life cycle. We can analyze any development style and map its activities to one or more high-level elements that may be overlapped, staffed, and iterated in various ways. Once your high-level activities have been mapped to the four QSM phases, the Milestones, WBS, and Skill Categories tabs in SLIM-Estimate can be used to identify incremental builds or other more detailed activities within each high-level phase.
This is where collecting and analyzing your historic data can dramatically improve the accuracy of your estimates. By analyzing the way your organization develops and deploys software, you can construct lifecycle templates tailored to your development environment and methods. Listed below are some general guidelines for dealing with software life cycle approaches that are unique, but which still fit into QSM's software measurement approach when some basic rules are applied for categorizing the life cycle phases.
In prototype or rapid application environments where the prototype will be used in the delivered architecture, include all of the time and effort for each of the "prototype cycles" performed (design, code, integration, and user approval) as well as the time and effort to integrate and stabilize the final product in Phase 3. If possible, determine the time and effort for Phase 2 by taking a percentage of the total time and effort spent defining software requirements
For enhancements, modifications, and large-scale maintenance efforts that are beyond the scope of the parent project’s Phase 4, include the time and effort for analysis of potential modifications/changes in Phase 2. Design modifications, coding and integration should be included in Phase 3.
In environments where prototypes are built to stabilize requirements and are subsequently discarded, include the time and effort spent building and verifying the prototypes in Phase 2. Do not count the discarded software in the delivered code count.
The earliest phase in the software life cycle where complete and consistent requirements and top-level, feasible plans for meeting them are developed.
The objectives of this phase are to develop a complete and technically feasible set of requirements for the system and to formulate the top-level approach and plan for their implementation. Typical products of these activities include:
This phase is complete when it is determined that building this system is feasible. A system-level requirements review may be held at the completion of this phase to determine the scope of the effort and the approach for Phase 2.
Phase 2 develops a technically feasible, modular design within the scope of the system requirements.
The objectives of this phase are to complete the system-level design by choosing the appropriate constituent technologies (hardware, software, etc.) and to allocate each system-level requirement to the appropriate technology. Software requirements are defined. The software top-level architecture is defined. Typical products include the following:
A design review (e.g., PDR) may be held during this phase to baseline the system design, software requirements, and software top-level architecture. The Concept Definition Phase normally overlaps the start of Phase 3 as the top-level software design is iterated and refined.
This phase produces a working system that implements the system specifications and meets system requirements in terms of performance and reliability. It typically begins with detailed logic design, continues through coding, unit testing, integration and system testing, and ends at full operational capability. The Construct & Test phase seeks to implement the software requirements as defined in Phase 2. Once the software requirements have been baselined, the activities in Phase 3 implement these requirements through software detail design, coding, and integration. Typical products include:
The phase starts on the date when the very first module design is started. The phase ends on the date when it is possible, for the first time, to deliver a fully functional system with 95% of the total defects identified. Subjectively, this is the point in the program where a fully functional system can be delivered with sufficient reliability to avoid customer returns.
The phase that usually coincides with the operations phase. It may include correcting errors revealed during system operation or enhancing the system to adapt to new user requirements, changes in the environment, and new hardware.
The objective of this phase is to provide the customer base with product support once the system is operational. In some life cycles, this phase includes continued testing to increase reliability and provide quality assurance to customers and certification authorities. During this phase, residual bugs in the system are corrected. In addition, development of later releases and functional enhancements may be performed to meet the new requirements of a changing world. The principal activities of this phase include:
In some life cycles, this phase is complete when management decides that the system is no longer of practical use and cuts off additional resources. Some time before this happens, management may seek more improvements and initiate a feasibility study for a new system to replace it. In other life cycles, this phase is complete when some sort of certification occurs. Evolution of the product beyond this point typically spawns new projects.
For each active phase, you should pick the staffing profile that best matches your historical effort buildup:
The application type tells us something about the complexity level of a project. Project data in the QSM database is stratified into nine application complexity domains, each with its own set of characteristics, size ranges, and productivity indices. Classifying completed projects by application domain will help you make apples to apples comparisons when analyzing project metrics or choosing appropriate projects to calibrate new estimates.